The U.S. Department of Energy and the North Carolina Clean Energy Technology Center are excited to announce that a new, modernized DSIRE is under construction. The new version of DSIRE will offer significant improvements over the current version, including expanded data accessibility and an array of new tools for site users. The new DSIRE site will be available in December 2014. Staff are currently working hard on the new version of DSIRE but are also maintaining the content of the current version of DSIRE. Thank you for your continued support and patience during this transition. We hope you are as excited for December as we are! The U.S. Department of Energy and the North Carolina Solar Center are excited to announce that a new, modernized DSIRE is under construction. The new version of DSIRE will offer significant improvements over the current version, including expanded data accessibility and an array of new tools for site users. The new DSIRE site will be available in the summer of 2014. Staff are currently working hard on the new DSIRE and are unfortunately only able to make minimal updates to the DSIRE website at this time. We apologize for any inconvenience and thank you for using DSIRE.

US Department Energy Efficiency and Renewable Energy
IREC North Carolina Solar Center
Home Glossary Links FAQs Contact About Twitter    Facebook
Vermont

Vermont

Incentives/Policies for Renewables & Efficiency

Printable Version
Interconnection Standards   

Last DSIRE Review: 06/03/2013
Program Overview:
State: Vermont
Incentive Type: Interconnection
Eligible Renewable/Other Technologies: Photovoltaics, Wind, Biomass, Fuel Cells, CHP/Cogeneration, Anaerobic Digestion, Fuel Cells using Renewable Fuels, Microturbines, Other Distributed Generation Technologies
Applicable Sectors: Commercial, Residential, Agricultural
Applicable Utilities:All utilities
System Capacity Limit:No limit specified
Standard Agreement:Yes
Insurance Requirements:Not addressed
External Disconnect Switch:Required
Net Metering Required:No (separate interconnection standards exist for net-metered systems 150 kW and under)
Web Site: http://psb.vermont.gov/statutesrulesandguidelines/currentrules
Authority 1:
Date Enacted:
Date Effective:
30 V.S.A. ยง 219a
1998 (subsequently amended)
1998
Authority 2:
Date Enacted:
Date Effective:
CVR 30 000 048. 5.100 (Net Metering Rules)
2001 (subsequently amended)
3/1/2001
Authority 3:
Date Effective:
CVR 30 000 048. 5.500 (Interconnection Rules)
9/10/2006
Summary:

Vermont has adopted separate interconnection standards for net-metered energy systems that are 150 kW or less, and for all other distributed-generation (DG) systems.

Interconnection Standards for Net-Metered Systems 150 kW or less

Vermont requires electric utilities to offer net metering to all customers with photovoltaic (PV) systems, wind-energy systems, fuel cells or biomass-energy systems until the cumulative generating capacity of net-metered systems equals 4% of a utility's peak demand.  The maximum system capacity for net metered systems is 500 kW. Interconnection of net-metered systems rated 150 kW or less are subject to the requirements described Appendix A of the net metering rules (5.100).

Net-metered PV systems must conform to applicable electrical safety, power-quality and interconnection requirements established by the National Electrical Code (NEC), the Institute of Electrical and Electronic Engineers (IEEE) and Underwriters Laboratories (UL). A utility may not charge additional standby, capacity or interconnection fees, or fees or charges other than the customary minimum monthly fee.

The following key provisions apply to all net-metered, interconnected systems 150 kW or less:

  • All systems must have a utility-accessible, lockable disconnect switch--unless the system is inverter based and the utility has waived the requirement in writing and in the case of small systems (less than 500 watts), where a lockable disconnect plug unit is acceptable if the customer files a proper application with the utility. The disconnect plug must be able to break load and must be utility-accessible.
  • Systems will be tested initially upon installation and once every two years to determine that anti-islanding controls are functioning correctly.
  • System owners must carry a minimum of $100,000 in general liability insurance for residential systems and $300,000 for non-residential sites.

Net metered systems must first complete an application for a "Certificate of Public Good for Interconnected Net Metered Power Systems," or register as a "Photovoltaic Systems that Are 10 kW (AC) or Less in Capacity," both of which are available on the Public Service Board's web site.

Interconnection Standards for Other Systems

In 2005, Vermont enacted legislation (Act 61) that established a statewide renewable portfolio goal and required the PSB to develop interconnection standards for DG up to 50 megawatts (MW) in capacity -- unless the PSB establishes a lower capacity in order to avoid federal preemption. In 2006, the PSB adopted interconnection standards for distributed-generation (DG) systems that are not net metered and not subject to Independent System Operator of New England (ISO-NE) interconnection rules or successor rules approved by the Federal Energy Regulatory Commission (FERC). These rules also apply to net-metered systems larger than 150 kW but smaller than 500 kW. Under this rule, utilities are required to designate an employee or office from which customers may obtain information regarding the application process. There is a standard application form and a nonrefundable application fee of $300. The PSB's DG interconnection rule does not specify a maximum system capacity.

DG systems that meet certain technical screening criteria are eligible for the "fast track" interconnection process, which requires no special studies. Systems not eligible for "fast track" interconnection require a feasibility study, a system-impact study, and/or a facilities study. Reasonable, specific timelines apply to "fast track" interconnection and general interconnection. During the interconnection process, either party may petition the PSB for resolution of a dispute.

A manual external disconnect switch is required. Systems must comply with an array of standards, including IEEE 1547 and UL 1741. Any equipment package will be considered certified for interconnection if it has been submitted, tested and listed by a nationally recognized testing and certification laboratory or approved by the U.S. Department of Energy.

The PSB has developed model interconnection documents, including a feasibility study agreement, a system impact study agreement, a facilities study agreement, an interconnection agreement, technical requirements and operator protocols. However, a customer and utility may also enter voluntarily into different arrangements.


 
Contact:
  Gregg Faber
Vermont Public Service Board
112 State Street, Drawer 20
Montpelier, VT 05620-2701
Phone: (802) 828-2358
E-Mail: gregg.faber@state.vt.us
Web Site: http://psb.vermont.gov/
NCSU - home
Disclaimer: The information presented on the DSIRE web site provides an unofficial overview of financial incentives and other policies. It does not constitute professional tax advice or other professional financial guidance, and it should not be used as the only source of information when making purchasing decisions, investment decisions or tax decisions, or when executing other binding agreements. Please refer to the individual contact provided below each summary to verify that a specific financial incentive or other policy applies to your project.

While the DSIRE staff strives to provide the best information possible, the DSIRE staff, the N.C. Solar Center, N.C. State University and the Interstate Renewable Energy Council, Inc. make no representations or warranties, either express or implied, concerning the accuracy, completeness, reliability or suitability of the information. The DSIRE staff, the N.C. Solar Center, N.C. State University and the Interstate Renewable Energy Council, Inc. disclaim all liability of any kind arising out of your use or misuse of the information contained or referenced on DSIRE Web pages.

Copyright 2013 - 2014 North Carolina State University, under NREL Subcontract No. XEU-0-99515-01. Permission granted only for personal or educational use, or for use by or on behalf of the U.S. government. North Carolina State University prohibits the unauthorized display, reproduction, sale, and/or distribution of all or portions of the content of the Database of State Incentives for Renewables and Efficiency (DSIRE) without prior, written consent.